Problem: Mr. Zahid signed a contract for building a road of 1920 meters long within 120 days. He employed 160 workers for this task. But after 24 days he found that only 1/8 of the task has been finished. If Mr. Zahid wants to finish the road in time how many additional workers he has to employ?

View all: DHAKA BANK | WRITTEN QUESTION (MATH) SOLVE | 2016

Correct Answer: 15 workers

Explanation:

Total workers = 160

Time to complete the task = 120 days

Remaining task =$1-\frac{1}{8}=\frac{7}{8}$

So, we get, by 120 days 1 task can be completed by = 160 Workers

By 1 day 1 task can be completed by = 160 x 120 workers.

By 96 days 1 task can be completed by = $\frac{160 x 120}{96}$ workers.

By 1 day $\frac{7}{8}$ task can be completed by =$\frac{160 x 120×7}{96×8}$ workers. = 175 workers.

Addition worker needed = 175 — 160 = 15 workers.

Write Reply...
You should read | Topics/Questions
User Avatar

Articles

0

Comments

0

Rating

0