Problem: A, B and C started a job which they can complete in 2 days. B can do the job in 5 days and C can do it in 4 days. After working for 1 day. \both 8 and C \left. How long would it take A to complete the rest of the job?

View all: CITY BANK LTD | OFFICER | WRITTEN QUESTION SOLVE(MATH) | 2001

Correct Answer: 10 days

Explanation:

A, B & C takes 2 days to complete = 1 work

A, B & C takes 1 days to complete =12

work

The rest of work = 1- 12

= 12

Only B takes 5 days to complete = 1 work

Only B takes 1 days to complete =15

work

Only C takes 4 days to complete = 1 work

Only C takes 1 days to complete =14

work

Jointly (B + C) can do in 1 day = 15

+ 14

=920

A can do 120

work in = 1 day

A can do 1 work in = 20 day

A can do 12

work in = 202

= 10 days