Problem: Two men and five women completed only one fourth portion of a job in 3 days. after 3 days. another man was included in the team and two days they completed another one fourth portion of the job. how many men (with no women) can complete the whole job in 4 days? …
View all: SONALI & JANATA BANK LTD (SO) IT WRITTEN QUESTION (MATH) SOLVE | 2018
Correct Answer: 6 men
Explanation:
2 men and 5 women require 3 days to complete $\frac{1}{4}$ Job
They complete $\frac{1}{4\times 3}$ =$\frac{1}{12}$ job in 1 day
3 men + 5 women require 2 days to complete $\frac{1}{12}$ job
They complete $\frac{1}{4\times 3}$ = $\frac{1}{8}$ in 1 days
3men + 5 women = $\frac{1}{8}$
2 men + 5 women = $\frac{1}{12}$
(-) 1 man = $\frac{1}{24}$
$\frac{1}{24}$ job is done in 1 day by 1 men
1 job is done in 1 day by 24 men1 job is done in 4 day by $\frac{1}{24}$ = 6 men.